এক নজরে পদ্মা বহুমুখী সেতু প্রকল্প
Component of the Project :
a) Main Bridge
b) River Training Works(RTW)
c) Janjira Approach Road & Selected Bridge End Facilities
d) Mawa Approach Road & Selected Bridge End Facilities
e) Service Area-2
f) Resettlement
g) Environment
h) Land Acquisition
i) CSC(Main Bridge & RTW)
j) CSC(Approach Roads & Service Area-2)
k) Engineering Support & Safety Team(ESST)
a) Main Bridge
b) River Training Works(RTW)
c) Janjira Approach Road & Selected Bridge End Facilities
d) Mawa Approach Road & Selected Bridge End Facilities
e) Service Area-2
f) Resettlement
g) Environment
h) Land Acquisition
i) CSC(Main Bridge & RTW)
j) CSC(Approach Roads & Service Area-2)
k) Engineering Support & Safety Team(ESST)
Main Bridge (6.15 km long):
Contractor : China Major Bridge Engineering Co. Ltd, China.
Contract Period : 4 years+1year (defect liability period).
Contract Cost : BDT: 12,133.39 crore.
Date of work order : November 26, 2014.
Date of Completion : .
Physical Progress of Work : Mobilization of equipments & procurement of materials as well as preparatory works such as geotechnical investigation, survey, steel fabrication of test pile, dredging and Contractor’s accommodation, stack yard, casting yard etc. construction are going on.
Contractor : China Major Bridge Engineering Co. Ltd, China.
Contract Period : 4 years+1year (defect liability period).
Contract Cost : BDT: 12,133.39 crore.
Date of work order : November 26, 2014.
Date of Completion : .
Physical Progress of Work : Mobilization of equipments & procurement of materials as well as preparatory works such as geotechnical investigation, survey, steel fabrication of test pile, dredging and Contractor’s accommodation, stack yard, casting yard etc. construction are going on.
River Training Works(14 km length):
Contractor : Sinohydro Corporation Limited, China.
Contract Period : 4 years+1year (defect liability period).
Contract Cost : BDT: 8707.81 crore.
Date of work order : December 31, 2014.
Date of Completion : .
Physical Progress of Work : Handed over land to Contractor, Mobilization of equipments & procurement of materials as well as Contractor’s accommodation, stack yard, casting yard etc. construction are going on.
Contractor : Sinohydro Corporation Limited, China.
Contract Period : 4 years+1year (defect liability period).
Contract Cost : BDT: 8707.81 crore.
Date of work order : December 31, 2014.
Date of Completion : .
Physical Progress of Work : Handed over land to Contractor, Mobilization of equipments & procurement of materials as well as Contractor’s accommodation, stack yard, casting yard etc. construction are going on.
Janjira Approach Road & Selected Bridge End Facilities (10.5 km length):
Contractor : AML-HCM JV.
Contract Period : 3 years+1year (defect liability period).
Contract Cost : BDT: 1097.40 crore.
Date of work order : October 08, 2013.
Physical Progress of Work : 29.10%.
Contractor : AML-HCM JV.
Contract Period : 3 years+1year (defect liability period).
Contract Cost : BDT: 1097.40 crore.
Date of work order : October 08, 2013.
Physical Progress of Work : 29.10%.
Mawa Approach Road & Selected Bridge End Facilities (1.5 km length):
Contractor : AML-HCM JV.
Contract Period : 2.5 years+1year (defect liability period).
Contract Cost : BDT: 193.40 crore.
Date of work order : January 27, 2014
Physical Progress of Work : 21.5%.
Contractor : AML-HCM JV.
Contract Period : 2.5 years+1year (defect liability period).
Contract Cost : BDT: 193.40 crore.
Date of work order : January 27, 2014
Physical Progress of Work : 21.5%.
Service Area-2:
Contractor : Abdul Monem Ltd.
Contract Period : 2.5 years+1year (defect liability period).
Contract Cost : BDT: 208.71 crore.
Date of work order : January 12, 2014
Physical Progress of Work : 12%.
Contractor : Abdul Monem Ltd.
Contract Period : 2.5 years+1year (defect liability period).
Contract Cost : BDT: 208.71 crore.
Date of work order : January 12, 2014
Physical Progress of Work : 12%.
Resettlement:
Total Additional Grant
Paid to the PAP : BDT: 500.71 crore(upto 31/12/2014).
Total no. of plots : 2698
No. of residential plots : 2618
No. of commercial plots : 80
977 plots have been handed over to the PAP out of approved 1045 plots(upto 31/12/2014).
Total Additional Grant
Paid to the PAP : BDT: 500.71 crore(upto 31/12/2014).
Total no. of plots : 2698
No. of residential plots : 2618
No. of commercial plots : 80
977 plots have been handed over to the PAP out of approved 1045 plots(upto 31/12/2014).
Environment:
Tree plantation has been started from 2012 and 55150 nos. of tree plantation has been completed up to-date.
Tree plantation has been started from 2012 and 55150 nos. of tree plantation has been completed up to-date.
Land Acquisition:
Land has been acquired 1408.54 hectre.
Land has been acquired 1408.54 hectre.
CSC(Main Bridge & RTW):
Consultant : Korea Expressway Corporation, South Korea & Associates.
Contract Period : 4 years+1year (defect liability period).
Contract Cost : BDT: 383.15 crore.
Date of Signing Contract : November 03, 2014.
Progress of Work : Deployment of manpower as well as supervision of works are going on.
Consultant : Korea Expressway Corporation, South Korea & Associates.
Contract Period : 4 years+1year (defect liability period).
Contract Cost : BDT: 383.15 crore.
Date of Signing Contract : November 03, 2014.
Progress of Work : Deployment of manpower as well as supervision of works are going on.
CSC(Approach Road & Service Area):
Consultant : Special Works Organization(SWO-West), Bangladesh Army in
association with BRTC, BUET.
Contract Period : 3 years+1year (defect liability period).
Contract Cost : BDT: 133.49 crore.
Date of Work Order : October 13, 2013.
Progress of Work : 40%.
Consultant : Special Works Organization(SWO-West), Bangladesh Army in
association with BRTC, BUET.
Contract Period : 3 years+1year (defect liability period).
Contract Cost : BDT: 133.49 crore.
Date of Work Order : October 13, 2013.
Progress of Work : 40%.
Engineering Support & Safety Team(ESST):
ESST : Bangladesh Army.
Contract Period : 4 years+1year (defect liability period).
Contract Cost : BDT: 72.14 crore.
Date of Work Order : October 13, 2013
Progress of Work : 40%.
ESST : Bangladesh Army.
Contract Period : 4 years+1year (defect liability period).
Contract Cost : BDT: 72.14 crore.
Date of Work Order : October 13, 2013
Progress of Work : 40%.